INVITATION TO BID
The City Vigan, through its Bids and Awards Committee (BAC), invites suppliers/manufacturers/distributors/contractors to apply for eligibility and to bid for the hereunder project:
Name of Project: | STREETSCAPE DEVELOPMENT (IMPROVEMENT OF STREET LIGHTS AT HERITAGE DISTRICT AND VARIOUS STREET IN VIGAN CITY |
Approved Budget for the Contract: | ₱ 13,774,575.91 |
Delivery Period: | 108 Days |
Prospective bidders should have experience in undertaking a similar project within the last 2 years with an amount of at least 50% of the proposed project for bidding. The Eligibility Check/Screening as well as the Preliminary Examination of Bids shall use non-discretionary “pass/fail” criteria. Post-qualification of the lowest calculated bid shall be conducted.
All particulars relative to Eligibility Statement and Screening, Bid Security, Performance Security, Pre-Bidding Conference(s), Evaluation of Bids, Post-Qualification and Award of Contract shall be governed by the pertinent provisions of R.A. 9184 and its Implementing Rules and Regulation (IRR).
The complete schedule of activities is listed, as follows:
BAC Activities | Schedule |
Issuance of Bid Documents | From November 23, 2019 until before the opening of bids (8:00 AM to 5:00 PM except Saturdays, Sundays and Holidays) |
Pre-Bid Conference | December 2, 2019 @ 2:00 PM |
Opening of Technical & Financial Proposal | December 16, 2019 @ 2:00 PM |
Bid Evaluation | December 17, 2019 |
Post Qualification | December 18, 2019 |
Approval of Resolution and Issuance of Notice of Award | December 19, 2019 |
Contract Preparation, Signing and Approval | December 20, 2019 |
Notice to Proceed | December 23, 2019 |
Bid Documents will be available only to prospective bidders upon payment of a non-refundable amount of ₱25,000.00 to the City of Vigan Cashier.
The City of Vigan assumes no responsibility whatsoever to compensate or indemnify bidders for any expenses incurred in the preparation of the Bid.
Approved by:
Dates of Publication: November 23, 2019 MILAGROS C. ALQUIZA
Website: www.vigancity.gov.ph
BAC Chairman
SUMMARY PROGRAM OF WORK
Name of Project: | STREETSCAPE DEVELOPMENT (IMPROVEMENT OF STREET LIGHTS AT HERITAGE DISTRICT AND VARIOUS STREET IN VIGAN CITY |
Approved Budget for the Contract: | ₱ 13,774,575.91 |
Delivery Period: | 108 Days |
SCOPE OF WORK
Item No. | Scope of Work | Qty | Unit |
I | Mobilization/Demobilization – | 1 | Lot |
II | Electrical works – Stand Alone Lights for Heritage Sights | 254 | set |
III | Interact City-General Led Connected Lighting | 167 | set |
IV | Construction Safety and Health Program | 3.60 | month |