NOTICE FOR NEGOTIATED PROCUREMENT

Publication: March 26, 2021
Closing: March 29, 2021

Name of Project Construction of Evacuation Center Phase II at Barangay Paratong, Vigan City
Approved Budget for the Contract
₱ 300,000.00
Contract Period 14 Days

Item No. JOB/ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST
1 Construction of Evacuation Center Phase II at Barangay Paratong, Vigan City 1 LS
******Scope of Works*******
Structure Excavation and Removal of Existing Slab
Concrete Works
Reinforcing Steel Bar
Tinsmithry Works/Steel Frame
Construction Safety and Health Program
xxxxxxxxxxxxxxxxxxxxxxxxxxxxx

*******************************************************************
For inquiries, please call BAC SECRETARIAT at (077) 722-8771-75 loc. 203 or email at bac@vigancity.gov.ph.

Approved:

MILAGROS C. ALQUIZA