Addendum No. 2-Supply or Fire Sprinkler System for the Four Storey Commercial Building and Display Center
BID AND AWARDS COMMITTEE
ADDENDUM NO. 002 s. 2018
This Addendum No. 002 is issued to modify or amend the publication of the project
Supply of Fire Sprinkler System at Four Storey Commercial and Display Center
The following item are to be change from the bid of the above-mentioned project:
Item # | Description | UOM | Quantity | Amount |
II | Construction of Safety and Health | months | 1.38 | 41,231.02 |
- Contract duration is reduced from 50 days to 42 days.
This shall form an integral part of the publication of the above mentioned project.
For guidance and information of all concerned.
Issued this 18th day of April, 2018
MILAGROS C. ALQUIZA